Smart Charger Configuration guide

Modified on Tue, 26 Nov at 2:12 PM

TABLE OF CONTENTS



Connecting to your charger via Bluetooth


Download the Morek EV Tool app



Establish Bluetooth connection with the charger 

  • Launch the "Morek EV Tool" app and allow it to use Bluetooth.



Android version may ask to use "Location Services". On some systems, this is how Bluetooth permission is called.


  • Identify the device you're trying to communicate with in the list. Tap on the device.  



Charger's name will correspond to it's serial number by default, or to the value of "CP name" set in the configuration.


  • Enter the password (12345678 by def.) and click "OK".



  • If default password is used, a prompt will appear to change it. If you do not wish to do it, tap "Cancel".



  • Congratulations! Proceed to configure the charger to your application.



Configuring the charger


MEV Tool App Configuration page


Below are screenshots of the Configuration page that user gets redirected to after successful Bluetooth connection is established with the charger.





Configuration parameter table 


For specific functions of each parameter, see the table below. 



Note that to use a chosen internet interface (WiFi/4G/LAN), it must be turned on at the top of the configuration page. Choose one according to installation plan and turn it on.



ParameterFunction
WiFi SSIDName of the WiFi network the charger connects to.
WiFi PasswordPassword for the WiFi network.
4G APNAccess Point Name for the 4G network configuration.
4G Account4G account name.
4G PasswordPassword for the 4G network connection.
IP AddressStatic IP address of the charger on the network.
Subnet MaskDefines the subnet range for the network.
Default GatewayGateway IP used for routing traffic outside the local network.
DNSDNS server for domain name resolution.
LAN DHCPEnables or disables DHCP for WiFi or LAN.
Server URLURL used to connect to OCPP server.
CP NameCharge point name. Used for Bluetooth discovery and as OCPP ID.
Authorization KeySecurity key (password) used for authorizing with OCPP server.
Output CurrentOutput current (per phase) limit in Amperes (e.g. 16 for 11 kW; 32 for 22 kW).
Charge ModeSpecifies the charging mode.
APP - for use with OCPP server
RFID - use local list for authorization
Plug&Charge - no authorization.
Power Distribution EnableEnables or disables DLM function. It is used to balance home loads and charging power to prevent overload. Used in single charger installations.
Sampling MethodThe method used for current sampling.
CT - Current transformers (e.g. MEVX02N1P5MCT)
Meter - Modbus RTU meter (e.g. MEVX03D3P0MID)
Home Power CurrentMaximum current limitation of home system / electrical panel in Amperes per phase.
Power Meter AddressThe address for the power meter (e.g. MEVX03D3P0MID). Inactive when CTs are used.
Phase RotationThe phase rotation. Inactive until DLB Mode is used.
Solar ModeEnables or disables the solar integration feature.
Solar Current From GridThe amount of current per phase that will supplement Solar Current from Grid.
Solar Stable TimeThe duration for stable solar input, after which charging will resume.
DLB ModeA mode to use with CT-Hub for group load management.
Diode DetectionEnables or disables diode detection for the charger.
Power Supply ModeThe type of power supply (e.g. TN system).




Saving the configuration


Changing a parameter will activate the "Set" button on the configuration page. 

Tap it to save the configuration in the charger.


After the message "Set successfully" is displayed, close the app.
Depending on the parameters changed, charger will reboot.
A single beep will indicate that charger is ready to use again.




The charger might indicate an error if configuration is incorrect according to installation. In that case, check Error Codes.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article